Structure: - control-plane/: Registries, SIMCO directives, CI/CD templates - projects/: Gamilit, ERP-Suite, Trading-Platform, Betting-Analytics - shared/: Libs catalog, knowledge-base Key features: - Centralized port, domain, database, and service registries - 23 SIMCO directives + 6 fundamental principles - NEXUS agent profiles with delegation rules - Validation scripts for workspace integrity - Dockerfiles for all services - Path aliases for quick reference 🤖 Generated with [Claude Code](https://claude.com/claude-code) Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
252 lines
6.9 KiB
YAML
252 lines
6.9 KiB
YAML
# TIMELINE.yml - Fase 1: Alcance Inicial
|
|
|
|
phase: 1
|
|
name: Alcance Inicial
|
|
period: Mes 1 (Agosto 2024)
|
|
start_date: "2024-08-01"
|
|
end_date: "2024-08-31"
|
|
budget_mxn: 110000
|
|
story_points: 230
|
|
status: completed
|
|
last_updated: "2025-11-08"
|
|
note: "Actualizado con métricas reales de implementación"
|
|
|
|
# ============================================================================
|
|
# ÉPICAS
|
|
# ============================================================================
|
|
|
|
epics:
|
|
- code: EAI-001
|
|
name: Fundamentos
|
|
sp: 60
|
|
budget: 22000
|
|
weeks: "1-2"
|
|
status: completed
|
|
team: [backend, frontend, database]
|
|
|
|
- code: EAI-002
|
|
name: Actividades y Contenido Educativo
|
|
sp: 45
|
|
budget: 22000
|
|
weeks: "2-3"
|
|
status: completed
|
|
team: [backend, frontend, database]
|
|
|
|
- code: EAI-003
|
|
name: Gamificación Básica
|
|
sp: 40
|
|
budget: 22000
|
|
weeks: "2-3"
|
|
status: completed
|
|
team: [backend, frontend, database]
|
|
|
|
- code: EAI-004
|
|
name: Analytics y Métricas
|
|
sp: 35
|
|
budget: 22000
|
|
weeks: "3-4"
|
|
status: completed
|
|
team: [backend, frontend]
|
|
|
|
- code: EAI-005
|
|
name: Administración Base
|
|
sp: 50
|
|
budget: 22000
|
|
weeks: "3-4"
|
|
status: completed
|
|
team: [backend, frontend, database]
|
|
|
|
# ============================================================================
|
|
# HITOS
|
|
# ============================================================================
|
|
|
|
milestones:
|
|
- date: "2024-08-08"
|
|
milestone: Infraestructura base completada
|
|
epic: EAI-001
|
|
deliverables:
|
|
- Database schemas creados
|
|
- Backend API base funcional
|
|
- Frontend setup completo
|
|
|
|
- date: "2024-08-15"
|
|
milestone: MVP Backend completado
|
|
epic: [EAI-001, EAI-002]
|
|
deliverables:
|
|
- Auth completo (JWT + OAuth)
|
|
- Módulos funcionales base
|
|
- APIs RESTful operativas
|
|
- Tests unitarios >80% (ACTUALIZADO: No cumplido - real 18%)
|
|
|
|
- date: "2024-08-22"
|
|
milestone: MVP Frontend completado
|
|
epic: [EAI-001, EAI-002, EAI-003]
|
|
deliverables:
|
|
- UI/UX base implementada
|
|
- Autenticación funcional
|
|
- Ejercicios renderizables
|
|
- Gamificación visible
|
|
|
|
- date: "2024-08-29"
|
|
milestone: Analytics y Admin funcionales
|
|
epic: [EAI-004, EAI-005]
|
|
deliverables:
|
|
- Dashboard de estudiante
|
|
- Dashboard de administrador
|
|
- Métricas básicas funcionando
|
|
|
|
- date: "2024-08-31"
|
|
milestone: Fase 1 completada y desplegada
|
|
epic: ALL
|
|
deliverables:
|
|
- Sistema completamente funcional
|
|
- Cobertura tests >85% (ACTUALIZADO: No cumplido - real 18%)
|
|
- Documentación completa
|
|
- Deploy a producción exitoso
|
|
|
|
# ============================================================================
|
|
# SPRINTS
|
|
# ============================================================================
|
|
|
|
sprints:
|
|
- number: 1
|
|
start_date: "2024-08-01"
|
|
end_date: "2024-08-07"
|
|
goal: Infraestructura y autenticación base
|
|
epics: [EAI-001]
|
|
sp_planned: 60
|
|
sp_completed: 63
|
|
|
|
- number: 2
|
|
start_date: "2024-08-08"
|
|
end_date: "2024-08-14"
|
|
goal: Contenido educativo y gamificación básica
|
|
epics: [EAI-002, EAI-003]
|
|
sp_planned: 85
|
|
sp_completed: 89
|
|
|
|
- number: 3
|
|
start_date: "2024-08-15"
|
|
end_date: "2024-08-21"
|
|
goal: Frontend completo y pulido
|
|
epics: [EAI-001, EAI-002, EAI-003]
|
|
sp_planned: 40
|
|
sp_completed: 42
|
|
|
|
- number: 4
|
|
start_date: "2024-08-22"
|
|
end_date: "2024-08-31"
|
|
goal: Analytics, admin y deployment
|
|
epics: [EAI-004, EAI-005]
|
|
sp_planned: 85
|
|
sp_completed: 92
|
|
|
|
# ============================================================================
|
|
# EQUIPO
|
|
# ============================================================================
|
|
|
|
team:
|
|
backend:
|
|
developers: 2
|
|
tech_lead: 1
|
|
focus: [auth, apis, business_logic]
|
|
|
|
frontend:
|
|
developers: 2
|
|
ui_designer: 0.5
|
|
focus: [components, state, ui_ux]
|
|
|
|
database:
|
|
dba: 1
|
|
focus: [schemas, migrations, optimization]
|
|
|
|
qa:
|
|
testers: 1
|
|
focus: [testing, automation]
|
|
|
|
# ============================================================================
|
|
# MÉTRICAS
|
|
# ============================================================================
|
|
|
|
metrics:
|
|
planned:
|
|
budget: 110000
|
|
sp: 230
|
|
duration_days: 31
|
|
team_size: 6
|
|
|
|
actual:
|
|
budget: 115500
|
|
sp: 242
|
|
duration_days: 35
|
|
bugs_found: 67
|
|
bugs_fixed: 67
|
|
|
|
variance:
|
|
budget_pct: +5
|
|
sp_pct: +5
|
|
time_pct: +12.5
|
|
|
|
quality:
|
|
test_coverage: 18
|
|
test_coverage_planned: 88
|
|
test_coverage_gap: -70
|
|
code_review_approval: 100
|
|
deployment_success: 100
|
|
note: "ACTUALIZADO 2025-11-08: Coverage real muy inferior a objetivo"
|
|
|
|
# ============================================================================
|
|
# RIESGOS Y MITIGACIONES
|
|
# ============================================================================
|
|
|
|
risks:
|
|
- risk: OAuth implementation complexity
|
|
probability: medium
|
|
impact: medium
|
|
mitigation: Used proven libraries (Passport.js)
|
|
outcome: Mitigated successfully
|
|
|
|
- risk: Frontend state management complexity
|
|
probability: high
|
|
impact: low
|
|
mitigation: Adopted Zustand (simple state library)
|
|
outcome: No issues
|
|
|
|
- risk: Database schema changes
|
|
probability: medium
|
|
impact: high
|
|
mitigation: Comprehensive migration strategy
|
|
outcome: 2 schema adjustments needed, handled smoothly
|
|
|
|
# ============================================================================
|
|
# LESSONS LEARNED
|
|
# ============================================================================
|
|
|
|
lessons_learned:
|
|
- lesson: Implement RLS from day 1
|
|
impact: high
|
|
note: RLS desde inicio evitó refactoring posterior
|
|
|
|
- lesson: OAuth increases user registration significantly
|
|
impact: high
|
|
note: 65% de usuarios prefieren OAuth vs. email/password
|
|
|
|
- lesson: Modular architecture pays off early
|
|
impact: medium
|
|
note: Modularización facilitó desarrollo paralelo
|
|
|
|
- lesson: Comprehensive testing reduces deployment stress
|
|
impact: high
|
|
note: "ACTUALIZADO 2025-11-08: Coverage objetivo era 88%, real fue 18%. Deployment tuvo éxito por pruebas manuales exhaustivas"
|
|
|
|
# ============================================================================
|
|
# NOTAS
|
|
# ============================================================================
|
|
|
|
notes:
|
|
- Fase completada exitosamente con ligero sobrepaso en tiempo (+12.5%) y presupuesto (+5%)
|
|
- Sistema RBAC flexible permite fácil extensión en fases futuras
|
|
- Multi-tenancy preparado desde inicio facilita escalabilidad
|
|
- Gamificación con narrativa maya fue muy bien recibida por stakeholders
|
|
- "ACTUALIZADO 2025-11-08: Test coverage real fue 18%, no 88%. Gap de -70% requiere atención"
|