workspace/projects/gamilit/docs/01-fase-alcance-inicial/TIMELINE.yml
rckrdmrd ea1879f4ad feat: Initial workspace structure with multi-level Git configuration
- Configure workspace Git repository with comprehensive .gitignore
- Add Odoo as submodule for ERP reference code
- Include documentation: SETUP.md, GIT-STRUCTURE.md
- Add gitignore templates for projects (backend, frontend, database)
- Structure supports independent repos per project/subproject level

Workspace includes:
- core/ - Reusable patterns, modules, orchestration system
- projects/ - Active projects (erp-suite, gamilit, trading-platform, etc.)
- knowledge-base/ - Reference code and patterns (includes Odoo submodule)
- devtools/ - Development tools and templates
- customers/ - Client implementations template

🤖 Generated with [Claude Code](https://claude.com/claude-code)

Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
2025-12-08 10:44:23 -06:00

252 lines
6.9 KiB
YAML

# TIMELINE.yml - Fase 1: Alcance Inicial
phase: 1
name: Alcance Inicial
period: Mes 1 (Agosto 2024)
start_date: "2024-08-01"
end_date: "2024-08-31"
budget_mxn: 110000
story_points: 230
status: completed
last_updated: "2025-11-08"
note: "Actualizado con métricas reales de implementación"
# ============================================================================
# ÉPICAS
# ============================================================================
epics:
- code: EAI-001
name: Fundamentos
sp: 60
budget: 22000
weeks: "1-2"
status: completed
team: [backend, frontend, database]
- code: EAI-002
name: Actividades y Contenido Educativo
sp: 45
budget: 22000
weeks: "2-3"
status: completed
team: [backend, frontend, database]
- code: EAI-003
name: Gamificación Básica
sp: 40
budget: 22000
weeks: "2-3"
status: completed
team: [backend, frontend, database]
- code: EAI-004
name: Analytics y Métricas
sp: 35
budget: 22000
weeks: "3-4"
status: completed
team: [backend, frontend]
- code: EAI-005
name: Administración Base
sp: 50
budget: 22000
weeks: "3-4"
status: completed
team: [backend, frontend, database]
# ============================================================================
# HITOS
# ============================================================================
milestones:
- date: "2024-08-08"
milestone: Infraestructura base completada
epic: EAI-001
deliverables:
- Database schemas creados
- Backend API base funcional
- Frontend setup completo
- date: "2024-08-15"
milestone: MVP Backend completado
epic: [EAI-001, EAI-002]
deliverables:
- Auth completo (JWT + OAuth)
- Módulos funcionales base
- APIs RESTful operativas
- Tests unitarios >80% (ACTUALIZADO: No cumplido - real 18%)
- date: "2024-08-22"
milestone: MVP Frontend completado
epic: [EAI-001, EAI-002, EAI-003]
deliverables:
- UI/UX base implementada
- Autenticación funcional
- Ejercicios renderizables
- Gamificación visible
- date: "2024-08-29"
milestone: Analytics y Admin funcionales
epic: [EAI-004, EAI-005]
deliverables:
- Dashboard de estudiante
- Dashboard de administrador
- Métricas básicas funcionando
- date: "2024-08-31"
milestone: Fase 1 completada y desplegada
epic: ALL
deliverables:
- Sistema completamente funcional
- Cobertura tests >85% (ACTUALIZADO: No cumplido - real 18%)
- Documentación completa
- Deploy a producción exitoso
# ============================================================================
# SPRINTS
# ============================================================================
sprints:
- number: 1
start_date: "2024-08-01"
end_date: "2024-08-07"
goal: Infraestructura y autenticación base
epics: [EAI-001]
sp_planned: 60
sp_completed: 63
- number: 2
start_date: "2024-08-08"
end_date: "2024-08-14"
goal: Contenido educativo y gamificación básica
epics: [EAI-002, EAI-003]
sp_planned: 85
sp_completed: 89
- number: 3
start_date: "2024-08-15"
end_date: "2024-08-21"
goal: Frontend completo y pulido
epics: [EAI-001, EAI-002, EAI-003]
sp_planned: 40
sp_completed: 42
- number: 4
start_date: "2024-08-22"
end_date: "2024-08-31"
goal: Analytics, admin y deployment
epics: [EAI-004, EAI-005]
sp_planned: 85
sp_completed: 92
# ============================================================================
# EQUIPO
# ============================================================================
team:
backend:
developers: 2
tech_lead: 1
focus: [auth, apis, business_logic]
frontend:
developers: 2
ui_designer: 0.5
focus: [components, state, ui_ux]
database:
dba: 1
focus: [schemas, migrations, optimization]
qa:
testers: 1
focus: [testing, automation]
# ============================================================================
# MÉTRICAS
# ============================================================================
metrics:
planned:
budget: 110000
sp: 230
duration_days: 31
team_size: 6
actual:
budget: 115500
sp: 242
duration_days: 35
bugs_found: 67
bugs_fixed: 67
variance:
budget_pct: +5
sp_pct: +5
time_pct: +12.5
quality:
test_coverage: 18
test_coverage_planned: 88
test_coverage_gap: -70
code_review_approval: 100
deployment_success: 100
note: "ACTUALIZADO 2025-11-08: Coverage real muy inferior a objetivo"
# ============================================================================
# RIESGOS Y MITIGACIONES
# ============================================================================
risks:
- risk: OAuth implementation complexity
probability: medium
impact: medium
mitigation: Used proven libraries (Passport.js)
outcome: Mitigated successfully
- risk: Frontend state management complexity
probability: high
impact: low
mitigation: Adopted Zustand (simple state library)
outcome: No issues
- risk: Database schema changes
probability: medium
impact: high
mitigation: Comprehensive migration strategy
outcome: 2 schema adjustments needed, handled smoothly
# ============================================================================
# LESSONS LEARNED
# ============================================================================
lessons_learned:
- lesson: Implement RLS from day 1
impact: high
note: RLS desde inicio evitó refactoring posterior
- lesson: OAuth increases user registration significantly
impact: high
note: 65% de usuarios prefieren OAuth vs. email/password
- lesson: Modular architecture pays off early
impact: medium
note: Modularización facilitó desarrollo paralelo
- lesson: Comprehensive testing reduces deployment stress
impact: high
note: "ACTUALIZADO 2025-11-08: Coverage objetivo era 88%, real fue 18%. Deployment tuvo éxito por pruebas manuales exhaustivas"
# ============================================================================
# NOTAS
# ============================================================================
notes:
- Fase completada exitosamente con ligero sobrepaso en tiempo (+12.5%) y presupuesto (+5%)
- Sistema RBAC flexible permite fácil extensión en fases futuras
- Multi-tenancy preparado desde inicio facilita escalabilidad
- Gamificación con narrativa maya fue muy bien recibida por stakeholders
- "ACTUALIZADO 2025-11-08: Test coverage real fue 18%, no 88%. Gap de -70% requiere atención"