- Configure workspace Git repository with comprehensive .gitignore - Add Odoo as submodule for ERP reference code - Include documentation: SETUP.md, GIT-STRUCTURE.md - Add gitignore templates for projects (backend, frontend, database) - Structure supports independent repos per project/subproject level Workspace includes: - core/ - Reusable patterns, modules, orchestration system - projects/ - Active projects (erp-suite, gamilit, trading-platform, etc.) - knowledge-base/ - Reference code and patterns (includes Odoo submodule) - devtools/ - Development tools and templates - customers/ - Client implementations template 🤖 Generated with [Claude Code](https://claude.com/claude-code) Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
421 lines
11 KiB
YAML
421 lines
11 KiB
YAML
# TIMELINE.yml - Fase 3: Extensiones
|
|
|
|
phase: 3
|
|
name: Extensiones Funcionales
|
|
period: Mes 3-4 (Octubre-Noviembre 2024)
|
|
start_date: "2024-10-01"
|
|
end_date: "2024-11-30"
|
|
budget_mxn: 105000
|
|
story_points: 390
|
|
status: completed
|
|
completion_rate: 100 # 6 épicas completas, 4 parciales en estado funcional
|
|
last_updated: "2025-11-08"
|
|
note: "Actualizado con métricas reales de implementación"
|
|
|
|
# ============================================================================
|
|
# ÉPICAS
|
|
# ============================================================================
|
|
|
|
epics:
|
|
# Épicas Completas
|
|
- code: EXT-001
|
|
name: Portal Maestros
|
|
sp: 50
|
|
budget: 15000
|
|
weeks: "1-2"
|
|
status: completed
|
|
team: [frontend, backend, ux]
|
|
priority: critical
|
|
completion: 100
|
|
|
|
- code: EXT-002
|
|
name: Admin Extendido
|
|
sp: 45
|
|
budget: 12000
|
|
weeks: "1-2"
|
|
status: completed
|
|
team: [frontend, backend]
|
|
priority: high
|
|
completion: 100
|
|
|
|
- code: EXT-003
|
|
name: Notificaciones
|
|
sp: 40
|
|
budget: 10000
|
|
weeks: "3-4"
|
|
status: completed
|
|
team: [backend, frontend]
|
|
priority: high
|
|
completion: 100
|
|
|
|
- code: EXT-004
|
|
name: Perfiles Avanzados
|
|
sp: 35
|
|
budget: 10000
|
|
weeks: "3-4"
|
|
status: completed
|
|
team: [frontend, backend]
|
|
priority: medium
|
|
completion: 100
|
|
|
|
- code: EXT-005
|
|
name: Reportes
|
|
sp: 50
|
|
budget: 12000
|
|
weeks: "5-6"
|
|
status: completed
|
|
team: [backend, frontend, analytics]
|
|
priority: high
|
|
completion: 100
|
|
|
|
- code: EXT-006
|
|
name: Gestión de Contenido
|
|
sp: 40
|
|
budget: 10000
|
|
weeks: "5-6"
|
|
status: completed
|
|
team: [backend, frontend]
|
|
priority: high
|
|
completion: 100
|
|
|
|
# Épicas Parciales
|
|
- code: EXT-007
|
|
name: LTI Integration
|
|
sp: 45
|
|
budget: 12000
|
|
weeks: "7-8"
|
|
status: partial
|
|
team: [backend]
|
|
priority: medium
|
|
completion: 40
|
|
|
|
- code: EXT-008
|
|
name: White Label
|
|
sp: 35
|
|
budget: 10000
|
|
weeks: "7-8"
|
|
status: partial
|
|
team: [frontend, backend]
|
|
priority: low
|
|
completion: 30
|
|
|
|
- code: EXT-009
|
|
name: Peer Challenges
|
|
sp: 30
|
|
budget: 8000
|
|
weeks: "9"
|
|
status: partial
|
|
team: [backend, frontend]
|
|
priority: low
|
|
completion: 50
|
|
|
|
- code: EXT-010
|
|
name: Parent Notifications
|
|
sp: 20
|
|
budget: 6000
|
|
weeks: "9"
|
|
status: partial
|
|
team: [backend, frontend]
|
|
priority: low
|
|
completion: 35
|
|
|
|
# ============================================================================
|
|
# HITOS
|
|
# ============================================================================
|
|
|
|
milestones:
|
|
- date: "2024-10-15"
|
|
milestone: Portal Maestros y Admin Extendido completados
|
|
epics: [EXT-001, EXT-002]
|
|
deliverables:
|
|
- Dashboard de maestros funcional
|
|
- Gestión de classrooms
|
|
- Admin tools extendidos
|
|
- Analytics agregados
|
|
|
|
- date: "2024-10-31"
|
|
milestone: Notificaciones y Perfiles completados
|
|
epics: [EXT-003, EXT-004]
|
|
deliverables:
|
|
- Sistema multi-canal de notificaciones
|
|
- Templates personalizables
|
|
- Perfiles enriquecidos
|
|
- Badges y estadísticas
|
|
|
|
- date: "2024-11-15"
|
|
milestone: Reportes y CMS completados
|
|
epics: [EXT-005, EXT-006]
|
|
deliverables:
|
|
- Custom report builder
|
|
- Exportación multi-formato
|
|
- Editor de contenido
|
|
- Workflow de aprobación
|
|
|
|
- date: "2024-11-30"
|
|
milestone: Épicas parciales en estado funcional
|
|
epics: [EXT-007, EXT-008, EXT-009, EXT-010]
|
|
deliverables:
|
|
- LTI 1.3 basic integration (40%)
|
|
- White label theming (30%)
|
|
- Peer challenges prototype (50%)
|
|
- Parent portal design (35%)
|
|
|
|
# ============================================================================
|
|
# SPRINTS
|
|
# ============================================================================
|
|
|
|
sprints:
|
|
- number: 9
|
|
start_date: "2024-10-01"
|
|
end_date: "2024-10-07"
|
|
goal: Portal Maestros - Backend y Dashboard
|
|
epics: [EXT-001]
|
|
sp_planned: 25
|
|
sp_completed: 26
|
|
|
|
- number: 10
|
|
start_date: "2024-10-08"
|
|
end_date: "2024-10-14"
|
|
goal: Portal Maestros - Features avanzados + Admin Extendido
|
|
epics: [EXT-001, EXT-002]
|
|
sp_planned: 35
|
|
sp_completed: 38
|
|
|
|
- number: 11
|
|
start_date: "2024-10-15"
|
|
end_date: "2024-10-21"
|
|
goal: Notificaciones multi-canal
|
|
epics: [EXT-003]
|
|
sp_planned: 20
|
|
sp_completed: 22
|
|
|
|
- number: 12
|
|
start_date: "2024-10-22"
|
|
end_date: "2024-10-31"
|
|
goal: Notificaciones + Perfiles
|
|
epics: [EXT-003, EXT-004]
|
|
sp_planned: 30
|
|
sp_completed: 32
|
|
|
|
- number: 13
|
|
start_date: "2024-11-01"
|
|
end_date: "2024-11-07"
|
|
goal: Reportes - Backend y data models
|
|
epics: [EXT-005]
|
|
sp_planned: 25
|
|
sp_completed: 27
|
|
|
|
- number: 14
|
|
start_date: "2024-11-08"
|
|
end_date: "2024-11-14"
|
|
goal: Reportes - UI + CMS inicio
|
|
epics: [EXT-005, EXT-006]
|
|
sp_planned: 35
|
|
sp_completed: 36
|
|
|
|
- number: 15
|
|
start_date: "2024-11-15"
|
|
end_date: "2024-11-21"
|
|
goal: CMS completo + Épicas parciales
|
|
epics: [EXT-006, EXT-007, EXT-008]
|
|
sp_planned: 30
|
|
sp_completed: 28
|
|
|
|
- number: 16
|
|
start_date: "2024-11-22"
|
|
end_date: "2024-11-30"
|
|
goal: Épicas parciales - prototipos funcionales
|
|
epics: [EXT-007, EXT-008, EXT-009, EXT-010]
|
|
sp_planned: 25
|
|
sp_completed: 23
|
|
|
|
# ============================================================================
|
|
# EQUIPO
|
|
# ============================================================================
|
|
|
|
team:
|
|
frontend:
|
|
developers: 3
|
|
focus: [dashboards, components, ux]
|
|
|
|
backend:
|
|
developers: 3
|
|
focus: [apis, services, integrations]
|
|
|
|
ux:
|
|
designers: 1
|
|
focus: [teacher_portal, admin_tools]
|
|
|
|
qa:
|
|
testers: 2
|
|
focus: [e2e_testing, integration_testing]
|
|
|
|
analytics:
|
|
analyst: 1
|
|
focus: [reporting, data_models]
|
|
|
|
# ============================================================================
|
|
# MÉTRICAS
|
|
# ============================================================================
|
|
|
|
metrics:
|
|
planned:
|
|
budget: 105000
|
|
sp: 390
|
|
duration_weeks: 8
|
|
team_size: 10
|
|
|
|
actual:
|
|
budget: 108500
|
|
sp: 405
|
|
duration_weeks: 9
|
|
epics_completed: 6
|
|
epics_partial: 4
|
|
|
|
variance:
|
|
budget_pct: +3
|
|
sp_pct: +4
|
|
time_pct: +12
|
|
|
|
quality:
|
|
test_coverage_before: 18
|
|
test_coverage_after: 18
|
|
test_coverage_planned: 92
|
|
test_coverage_gap: -74
|
|
bugs_found: 45
|
|
bugs_fixed: 42
|
|
critical_bugs: 0
|
|
note: "ACTUALIZADO 2025-11-08: Coverage real muy inferior a objetivo"
|
|
|
|
deliverables:
|
|
backend_modules: 10
|
|
frontend_components: 80
|
|
api_endpoints: 45
|
|
database_tables: 15
|
|
tests_written: 2
|
|
tests_written_planned: 320
|
|
tests_gap: -318
|
|
note: "ACTUALIZADO 2025-11-08: Solo 2 tests encontrados (gamification/ranks), gap crítico de 318 tests"
|
|
|
|
# ============================================================================
|
|
# IMPACTO TÉCNICO
|
|
# ============================================================================
|
|
|
|
technical_impact:
|
|
backend:
|
|
new_modules: 10
|
|
new_services: 25
|
|
new_endpoints: 45
|
|
lines_of_code: ~15000
|
|
|
|
frontend:
|
|
new_features: 6
|
|
new_components: 80
|
|
new_pages: 15
|
|
lines_of_code: ~18000
|
|
|
|
database:
|
|
new_tables: 15
|
|
new_indexes: 35
|
|
new_functions: 8
|
|
new_views: 6
|
|
|
|
testing:
|
|
unit_tests: 2
|
|
integration_tests: 0
|
|
e2e_tests: 0
|
|
total_tests: 2
|
|
unit_tests_planned: 180
|
|
integration_tests_planned: 85
|
|
e2e_tests_planned: 55
|
|
total_tests_planned: 320
|
|
note: "ACTUALIZADO 2025-11-08: Solo módulo gamification/ranks tiene tests (2 archivos)"
|
|
|
|
# ============================================================================
|
|
# RIESGOS Y MITIGACIONES
|
|
# ============================================================================
|
|
|
|
risks:
|
|
- risk: Portal Maestros muy complejo
|
|
probability: high
|
|
impact: high
|
|
mitigation: Sprints dedicados + UX involvement temprano
|
|
outcome: Completado con +5% variance en tiempo
|
|
|
|
- risk: Sistema de notificaciones - infrastructure overhead
|
|
probability: medium
|
|
impact: medium
|
|
mitigation: Uso de servicios cloud (SendGrid, FCM)
|
|
outcome: Implementación exitosa
|
|
|
|
- risk: Custom report builder muy ambicioso
|
|
probability: medium
|
|
impact: medium
|
|
mitigation: MVP primero, features avanzados después
|
|
outcome: MVP completado, features avanzados 80%
|
|
|
|
- risk: Épicas parciales no completadas
|
|
probability: high
|
|
impact: low
|
|
mitigation: Re-priorización según contratos enterprise
|
|
outcome: Estado funcional alcanzado
|
|
|
|
# ============================================================================
|
|
# LESSONS LEARNED
|
|
# ============================================================================
|
|
|
|
lessons_learned:
|
|
- lesson: Portal Maestros es feature #1 para adopción enterprise
|
|
impact: critical
|
|
note: Instituciones requieren herramientas de gestión robustas
|
|
|
|
- lesson: Notificaciones multi-canal requieren infrastructure dedicada
|
|
impact: high
|
|
note: No subestimar complejidad de delivery confiable
|
|
|
|
- lesson: Custom report builder provee diferenciación
|
|
impact: high
|
|
note: Features más solicitados vs templates predefinidos
|
|
|
|
- lesson: CMS workflow de aprobación es esencial
|
|
impact: medium
|
|
note: Calidad de contenido crítica para valor educativo
|
|
|
|
- lesson: Épicas parciales requieren contratos enterprise
|
|
impact: medium
|
|
note: LTI y White Label dependen de clientes específicos
|
|
|
|
- lesson: Testing E2E crítico para features complejos
|
|
impact: high
|
|
note: "ACTUALIZADO 2025-11-08: Objetivo era 320 tests (180 unit, 85 integration, 55 e2e). Real: 2 tests. Portal Maestros y Reportes funcionan gracias a testing manual exhaustivo, pero requieren urgentemente tests automatizados"
|
|
|
|
# ============================================================================
|
|
# DEPENDENCIAS HABILITADAS
|
|
# ============================================================================
|
|
|
|
enabled_features:
|
|
- Adopción institucional mediante Portal Maestros
|
|
- Gestión a escala con Admin Extendido
|
|
- Engagement mejorado con Notificaciones
|
|
- Data-driven decisions con Reportería
|
|
- Escalabilidad de contenido con CMS
|
|
- Integración LMS básica (LTI parcial)
|
|
- Multi-tenancy básico (White Label parcial)
|
|
|
|
# ============================================================================
|
|
# NOTAS
|
|
# ============================================================================
|
|
|
|
notes:
|
|
- Fase completada con +3% budget variance y +12% time variance
|
|
- 6 épicas completas al 100%
|
|
- 4 épicas parciales en estado funcional (promedio 39%)
|
|
- Portal Maestros es el feature más exitoso de la fase
|
|
- Sistema de notificaciones enterprise-ready
|
|
- Custom report builder provee diferenciación competitiva
|
|
- Épicas parciales dependen de roadmap 2025 y contratos enterprise
|
|
- "ACTUALIZADO 2025-11-08: Test coverage real 18% (objetivo era 92%)"
|
|
- "ACTUALIZADO 2025-11-08: Solo 2 tests implementados de 320 planificados"
|
|
- "ACTUALIZADO 2025-11-08: Funcionalidad completa y deployment exitoso gracias a testing manual exhaustivo"
|
|
- "ACTUALIZADO 2025-11-08: Gap de testing (-318 tests) representa deuda técnica crítica que debe atenderse"
|