workspace/projects/gamilit/docs/03-fase-extensiones/TIMELINE.yml
rckrdmrd ea1879f4ad feat: Initial workspace structure with multi-level Git configuration
- Configure workspace Git repository with comprehensive .gitignore
- Add Odoo as submodule for ERP reference code
- Include documentation: SETUP.md, GIT-STRUCTURE.md
- Add gitignore templates for projects (backend, frontend, database)
- Structure supports independent repos per project/subproject level

Workspace includes:
- core/ - Reusable patterns, modules, orchestration system
- projects/ - Active projects (erp-suite, gamilit, trading-platform, etc.)
- knowledge-base/ - Reference code and patterns (includes Odoo submodule)
- devtools/ - Development tools and templates
- customers/ - Client implementations template

🤖 Generated with [Claude Code](https://claude.com/claude-code)

Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
2025-12-08 10:44:23 -06:00

421 lines
11 KiB
YAML

# TIMELINE.yml - Fase 3: Extensiones
phase: 3
name: Extensiones Funcionales
period: Mes 3-4 (Octubre-Noviembre 2024)
start_date: "2024-10-01"
end_date: "2024-11-30"
budget_mxn: 105000
story_points: 390
status: completed
completion_rate: 100 # 6 épicas completas, 4 parciales en estado funcional
last_updated: "2025-11-08"
note: "Actualizado con métricas reales de implementación"
# ============================================================================
# ÉPICAS
# ============================================================================
epics:
# Épicas Completas
- code: EXT-001
name: Portal Maestros
sp: 50
budget: 15000
weeks: "1-2"
status: completed
team: [frontend, backend, ux]
priority: critical
completion: 100
- code: EXT-002
name: Admin Extendido
sp: 45
budget: 12000
weeks: "1-2"
status: completed
team: [frontend, backend]
priority: high
completion: 100
- code: EXT-003
name: Notificaciones
sp: 40
budget: 10000
weeks: "3-4"
status: completed
team: [backend, frontend]
priority: high
completion: 100
- code: EXT-004
name: Perfiles Avanzados
sp: 35
budget: 10000
weeks: "3-4"
status: completed
team: [frontend, backend]
priority: medium
completion: 100
- code: EXT-005
name: Reportes
sp: 50
budget: 12000
weeks: "5-6"
status: completed
team: [backend, frontend, analytics]
priority: high
completion: 100
- code: EXT-006
name: Gestión de Contenido
sp: 40
budget: 10000
weeks: "5-6"
status: completed
team: [backend, frontend]
priority: high
completion: 100
# Épicas Parciales
- code: EXT-007
name: LTI Integration
sp: 45
budget: 12000
weeks: "7-8"
status: partial
team: [backend]
priority: medium
completion: 40
- code: EXT-008
name: White Label
sp: 35
budget: 10000
weeks: "7-8"
status: partial
team: [frontend, backend]
priority: low
completion: 30
- code: EXT-009
name: Peer Challenges
sp: 30
budget: 8000
weeks: "9"
status: partial
team: [backend, frontend]
priority: low
completion: 50
- code: EXT-010
name: Parent Notifications
sp: 20
budget: 6000
weeks: "9"
status: partial
team: [backend, frontend]
priority: low
completion: 35
# ============================================================================
# HITOS
# ============================================================================
milestones:
- date: "2024-10-15"
milestone: Portal Maestros y Admin Extendido completados
epics: [EXT-001, EXT-002]
deliverables:
- Dashboard de maestros funcional
- Gestión de classrooms
- Admin tools extendidos
- Analytics agregados
- date: "2024-10-31"
milestone: Notificaciones y Perfiles completados
epics: [EXT-003, EXT-004]
deliverables:
- Sistema multi-canal de notificaciones
- Templates personalizables
- Perfiles enriquecidos
- Badges y estadísticas
- date: "2024-11-15"
milestone: Reportes y CMS completados
epics: [EXT-005, EXT-006]
deliverables:
- Custom report builder
- Exportación multi-formato
- Editor de contenido
- Workflow de aprobación
- date: "2024-11-30"
milestone: Épicas parciales en estado funcional
epics: [EXT-007, EXT-008, EXT-009, EXT-010]
deliverables:
- LTI 1.3 basic integration (40%)
- White label theming (30%)
- Peer challenges prototype (50%)
- Parent portal design (35%)
# ============================================================================
# SPRINTS
# ============================================================================
sprints:
- number: 9
start_date: "2024-10-01"
end_date: "2024-10-07"
goal: Portal Maestros - Backend y Dashboard
epics: [EXT-001]
sp_planned: 25
sp_completed: 26
- number: 10
start_date: "2024-10-08"
end_date: "2024-10-14"
goal: Portal Maestros - Features avanzados + Admin Extendido
epics: [EXT-001, EXT-002]
sp_planned: 35
sp_completed: 38
- number: 11
start_date: "2024-10-15"
end_date: "2024-10-21"
goal: Notificaciones multi-canal
epics: [EXT-003]
sp_planned: 20
sp_completed: 22
- number: 12
start_date: "2024-10-22"
end_date: "2024-10-31"
goal: Notificaciones + Perfiles
epics: [EXT-003, EXT-004]
sp_planned: 30
sp_completed: 32
- number: 13
start_date: "2024-11-01"
end_date: "2024-11-07"
goal: Reportes - Backend y data models
epics: [EXT-005]
sp_planned: 25
sp_completed: 27
- number: 14
start_date: "2024-11-08"
end_date: "2024-11-14"
goal: Reportes - UI + CMS inicio
epics: [EXT-005, EXT-006]
sp_planned: 35
sp_completed: 36
- number: 15
start_date: "2024-11-15"
end_date: "2024-11-21"
goal: CMS completo + Épicas parciales
epics: [EXT-006, EXT-007, EXT-008]
sp_planned: 30
sp_completed: 28
- number: 16
start_date: "2024-11-22"
end_date: "2024-11-30"
goal: Épicas parciales - prototipos funcionales
epics: [EXT-007, EXT-008, EXT-009, EXT-010]
sp_planned: 25
sp_completed: 23
# ============================================================================
# EQUIPO
# ============================================================================
team:
frontend:
developers: 3
focus: [dashboards, components, ux]
backend:
developers: 3
focus: [apis, services, integrations]
ux:
designers: 1
focus: [teacher_portal, admin_tools]
qa:
testers: 2
focus: [e2e_testing, integration_testing]
analytics:
analyst: 1
focus: [reporting, data_models]
# ============================================================================
# MÉTRICAS
# ============================================================================
metrics:
planned:
budget: 105000
sp: 390
duration_weeks: 8
team_size: 10
actual:
budget: 108500
sp: 405
duration_weeks: 9
epics_completed: 6
epics_partial: 4
variance:
budget_pct: +3
sp_pct: +4
time_pct: +12
quality:
test_coverage_before: 18
test_coverage_after: 18
test_coverage_planned: 92
test_coverage_gap: -74
bugs_found: 45
bugs_fixed: 42
critical_bugs: 0
note: "ACTUALIZADO 2025-11-08: Coverage real muy inferior a objetivo"
deliverables:
backend_modules: 10
frontend_components: 80
api_endpoints: 45
database_tables: 15
tests_written: 2
tests_written_planned: 320
tests_gap: -318
note: "ACTUALIZADO 2025-11-08: Solo 2 tests encontrados (gamification/ranks), gap crítico de 318 tests"
# ============================================================================
# IMPACTO TÉCNICO
# ============================================================================
technical_impact:
backend:
new_modules: 10
new_services: 25
new_endpoints: 45
lines_of_code: ~15000
frontend:
new_features: 6
new_components: 80
new_pages: 15
lines_of_code: ~18000
database:
new_tables: 15
new_indexes: 35
new_functions: 8
new_views: 6
testing:
unit_tests: 2
integration_tests: 0
e2e_tests: 0
total_tests: 2
unit_tests_planned: 180
integration_tests_planned: 85
e2e_tests_planned: 55
total_tests_planned: 320
note: "ACTUALIZADO 2025-11-08: Solo módulo gamification/ranks tiene tests (2 archivos)"
# ============================================================================
# RIESGOS Y MITIGACIONES
# ============================================================================
risks:
- risk: Portal Maestros muy complejo
probability: high
impact: high
mitigation: Sprints dedicados + UX involvement temprano
outcome: Completado con +5% variance en tiempo
- risk: Sistema de notificaciones - infrastructure overhead
probability: medium
impact: medium
mitigation: Uso de servicios cloud (SendGrid, FCM)
outcome: Implementación exitosa
- risk: Custom report builder muy ambicioso
probability: medium
impact: medium
mitigation: MVP primero, features avanzados después
outcome: MVP completado, features avanzados 80%
- risk: Épicas parciales no completadas
probability: high
impact: low
mitigation: Re-priorización según contratos enterprise
outcome: Estado funcional alcanzado
# ============================================================================
# LESSONS LEARNED
# ============================================================================
lessons_learned:
- lesson: Portal Maestros es feature #1 para adopción enterprise
impact: critical
note: Instituciones requieren herramientas de gestión robustas
- lesson: Notificaciones multi-canal requieren infrastructure dedicada
impact: high
note: No subestimar complejidad de delivery confiable
- lesson: Custom report builder provee diferenciación
impact: high
note: Features más solicitados vs templates predefinidos
- lesson: CMS workflow de aprobación es esencial
impact: medium
note: Calidad de contenido crítica para valor educativo
- lesson: Épicas parciales requieren contratos enterprise
impact: medium
note: LTI y White Label dependen de clientes específicos
- lesson: Testing E2E crítico para features complejos
impact: high
note: "ACTUALIZADO 2025-11-08: Objetivo era 320 tests (180 unit, 85 integration, 55 e2e). Real: 2 tests. Portal Maestros y Reportes funcionan gracias a testing manual exhaustivo, pero requieren urgentemente tests automatizados"
# ============================================================================
# DEPENDENCIAS HABILITADAS
# ============================================================================
enabled_features:
- Adopción institucional mediante Portal Maestros
- Gestión a escala con Admin Extendido
- Engagement mejorado con Notificaciones
- Data-driven decisions con Reportería
- Escalabilidad de contenido con CMS
- Integración LMS básica (LTI parcial)
- Multi-tenancy básico (White Label parcial)
# ============================================================================
# NOTAS
# ============================================================================
notes:
- Fase completada con +3% budget variance y +12% time variance
- 6 épicas completas al 100%
- 4 épicas parciales en estado funcional (promedio 39%)
- Portal Maestros es el feature más exitoso de la fase
- Sistema de notificaciones enterprise-ready
- Custom report builder provee diferenciación competitiva
- Épicas parciales dependen de roadmap 2025 y contratos enterprise
- "ACTUALIZADO 2025-11-08: Test coverage real 18% (objetivo era 92%)"
- "ACTUALIZADO 2025-11-08: Solo 2 tests implementados de 320 planificados"
- "ACTUALIZADO 2025-11-08: Funcionalidad completa y deployment exitoso gracias a testing manual exhaustivo"
- "ACTUALIZADO 2025-11-08: Gap de testing (-318 tests) representa deuda técnica crítica que debe atenderse"